OITDC HX Maintenance 12/10

Date(s): Friday, December 10, 2021, from 8 - 10am

Purpose:

Services Affected:

On 12/10 starting at 8 AM, Vertiv will be onsite at the OIT data center performing preventative maintenance on the heat exchanger (HX) unit. They will be only doing non-interruptive work, so there should be no down time expected of the cooling in the room. The PM should last 1-2 hours, being completed by 10 AM.

If you have any questions or concerns please contact Alex Giesler at 949-824-9494.

Service Maintenance Status: Resolved

Resolution:

« View All Planned Maintenance Announcements