Date(s): October 23, 2019 from 730 - 1pm
Purpose:
Services Affected:
On 10/23/19 at approximately 7:30 AM, we will be working with Facilities to remove old and unused outlets and breakers from our PDU1 panels. They will be shut off one at a time so as to limit concurrent downtimes. When the work is complete around 1 PM, the panels will be back on and normal power function will return to the data center. This work will affect one customer group only, and we are working with that group to limit their exposure to this work.
If you have any questions, please contact Alex Giesler at 949-824-9494.
Service Maintenance Status: Resolved
Resolution: